Hlcaluminium -
1. Tools used for curtain wall: toothless saw blade cutting machine, hand electric drill, impact electric drill, nail gun, various specifications of drill flowers, wrench, screwdriver, hand hammer, ink line, line sag, nylon line, steel tape measure, electric welding machine , Oxygen cutting equipment, passive suction cups, electric hanging blue, glue injection guns, pneumatic riveting guns, seat belts, etc.
2. Preparatory work before materials enter the site This part of the work is the initial stage of the project. Based on the principle of construction service, it should be completed on schedule, with guaranteed quality and guaranteed quantity.
details as follows:
(1) After the contract is signed, the designer shall propose the material plan for the project in the shortest possible time according to the architectural drawing and the curtain wall project plan of the project.
(2) The project manager department and the production department cooperate with each other, make the processing plan of the project according to the construction schedule and the actual situation of the project site, reasonably organize and arrange the production, and ensure the timely arrival of the products.
3. Installation process flow → connecting parts of fixed frame → fixed frame → installation of aluminum plate → closing structure treatment → inspection There should be a product certificate. 2. If profiled steel keel is used for the skeleton of the curtain wall, its specification and shape should meet the design requirements, and should be treated with rust removal and anti-rust treatment. 3. For aluminum plate installation, when the design has no requirements, core-pulling aluminum rivets should be used, and a rubber ring must be placed in the middle.
Blind rivet spacing should be controlled within 100-150mm.
(1) Pay-off Fix the skeleton, and bounce the position of the skeleton to the base layer. The skeleton is fixed on the main structure, and the quality of the main structure is checked before the line is released.
(2) Connectors for fixing the skeleton Weld the connecting pieces on the columns of the main structure to fix the skeleton.
(3) Fixed skeleton The skeleton is pre-treated with anti-corrosion. The position of the installation frame is accurate and the combination is firm.
After installation, check the centerline, surface level, etc. In order to ensure the installation accuracy of the board, it is advisable to use the theodolite to penetrate the beam and mullion members. Properly handle deformation joints, settlement joints, and variable cross-sections to make them meet the requirements of use.
(4) Installation of aluminum plate The installation and fixation of the aluminum plate should be firm and reliable, simple and easy.
1. The gap between the board and the board should be treated internally to make it flat and smooth.
2. After the aluminum plate is installed, cover and protect the parts that are easy to be polluted with plastic film or other materials.
C. Construction plan of aluminum canopy 1. Tools and tools used in aluminum canopy: toothless saw blade cutting machine, hand electric drill, impact electric drill, nail gun, various specifications of drill flowers, wrenches, screwdrivers, hand hammers, ink lines, lines Vertical, nylon wire, steel tape measure, electric welding machine, oxygen cutting equipment, glue injection gun, pneumatic riveting gun, safety belt, etc. 2. Preparatory work before materials enter the site This part of the work is the initial stage of the project. Based on the principle of construction services, it should be completed on schedule, with guaranteed quality and guaranteed quantity. The details are as follows:
(1) After the contract is signed, the designer shall propose the material plan for the project in the shortest possible time according to the architectural drawing and the curtain wall project plan of the project.
(2) The project manager department and the production department cooperate with each other, make the processing plan of the project according to the construction schedule and the actual situation of the project site, reasonably organize and arrange the production, and ensure the timely arrival of the products.
Third, the installation process Set up.