According to the manufacturer of aluminium composite panels, when installing aluminium composite panels,
the outer edge of the panels and the horizontal vertical control line should be measured and placed accurately according to the design and construction site.
Then the centre line of the vertical frame of the skeleton according to the design grid size to the structure,
in the measurement of the line should be in the wind not more than 4 levels of weather conditions,
individual cases should also take windproof measures. For the installation of anchorages,
pre-buried parts should be used as far as possible, and in the absence of pre-buried parts, post-buried parts should be used,
the structural form of the buried parts should meet the design requirements,
and the anchor bolts should be tested on site to meet the strength requirements before use.
The anchor is generally composed of buried plate and connecting angle code,
construction in accordance with the design requirements in the vertical frame has been measured and placed
on the centre line accurately marked out buried plate position, after punching holes will be buried fixed,
and the vertical frame centre line lead to the buried, and then calculate the position of connecting angle code,
in the buried plate scribe mark, the same vertical frame on the same side of the connecting angle code position to pull through the line detection,
can not be deviated.
After the position of the corner code is determined, the corner code will be welded to the buried plate in this position,
the width and length of the weld should meet the design requirements,
after welding the weld should be redone to prevent rust treatment, generally painted with anti-rust paint two times.