When the aluminium composite panel wholesale products are dry hanging construction,
the line should be placed according to the actual centre line and elevation point of the civil construction,
how to do it specifically?
The design of the finish is based on the axis of the building.
The aluminium composite panel skeleton is composed of horizontal and vertical parts, so firstly,
the position line of the vertical rod is played, and then the anchorage point of the vertical rod is determined.
Installation of fixed connections on the basis of the release line, fixed connections by welding,
rust-proof paint at the welded seam second degree.
Install the skeleton to install the skeleton by welding method, install at any time to check the elevation,
the position of the centre line, and at the same time the section connection weld to do rust-proof paint treatment,
fixed connections to do hidden inspection records including the length of the connection weld, thickness,
location buried elevation, quantity, embedded depth.
When installing the aluminium composite panel on the inner frame of the profile,
the screw holes should be tapped and milled first,
and the aluminium composite panel finish should be fixed on the profile steel skeleton piece by piece with rivets;
the gap between the panel and the plate should be 10-15㎜ before injecting the silicone weatherproof sealant.