Hlcaluminium -aluminium composite Panels Manufacturers
Installation method of aluminum plastic panels: Directory construction process quality standard products protection quality record construction process
1. Process process
Bouncing Wall → Dragon Skill Society → Install the Dragon Boss → Install the chitin → anticorrosive treatment →
Install the cover panel → install the pressure bar
2. Operation process
(1) Bullet
The horizontal line and vertical vertical line pop up on the substrate to control the position of the partition keel installation, the straightness and fixing point of the grille.
(2) Installation of wall keel:
1) Fix the top of the bomb line along the top and the ground keel, and the keels that are handed in each of them should be straight. The distance between the fixed point should not be greater than 1 meter.
Between the border keel and the matrix, the sealing strip should be installed according to the design requirements.
2) Attonable keels should be used at doors and windows or special nodes, and the installation should meet the design requirements.
(3) Installation of Jiu Piece
When the surface of the nine splint is installed, when the oil perculent and the glaze are needed, it should be paved with flat, and it should be tightly set. There must be no wrinkles, cracks, and pores.
The nine splints are fixed with straight nails. If it is fixed with nails, the nail distance is 80-150mm, the nail cap should be flattened and nailed to the plate surface 0.5-1mm; When the nine grasses are painted with coatings such as cleaning oil, the wood grain and color of the adjacent plate should be approximate. Requesting of materials such as sound insulation, insulation, fire prevention, and other materials; generally use glass cotton or 30-100mm rock wool plates for sound insulation and fire treatment; 50 to 100mm benzene boards are used for insulation treatment.
Close the cover panel.
When the wall is decorated with a nine splint, the corner of the yang should be used as a corner; the hard fiber plate is soaked in water, and it is installed after natural shade.
When the nine splints are fixed with a wooden pressure strip, the nail distance should not be greater than 200mm.
When a nine splint is installed on the wall, the corner should be made at the corner to prevent the corner of the board and increase the decoration.
(4) Establishment of aluminum plastic panels
The aluminum -plastic plate uses a single -sided aluminum -plastic plate. According to the design requirements, it is cut into the required shape. The glue is pasted on the sealing bottom plate in advance, and the appropriate rubber seam can be left according to the design requirements.
1. Main control project
(1) The material, variety, specifications, and styles of skeleton wood and cover plate should meet the design requirements and construction specifications.
(2) The wooden skeleton must be firmly installed, no loose, and the position is correct.
(3) There are no defects such as departure, warp, cracking, lack of corners, etc., and the installation must be firm.
2. Basic items
(1) The wooden skeleton should be straight, without bending, deformation and splitting.
(2) The surface of the cover panel should be straight, clean, pollution -free, hemp, and hammer printing. The color should be the same.
Finished product protection1. When installing the wooden skeleton and cover panel of the wall, pay attention to protecting various pipelines in the ceiling and a boiling rod of the wooden skeleton.
2. The doors and windows that have been installed in the construction site should pay attention to protection and prevent damage.
3. Striped wood skeleton materials, especially the covering panel materials, should be managed properly in the process of entering, storage, and use, so that it does not deform, non -moisture, damage, and pollution.
Quality Record1. The materials shall have a certificate and environmental inspection report.